Centennial Trail Asphalt Overlay
Project summary
Beginning in mid-April, the first 14 miles of the Spokane River Centennial Trail will temporarily close while Parks resurfaces the trail with a new layer of asphalt. The project is anticipated for completion in early September.
- Location: Spokane River Centennial State Park Trail
- Estimated start date: Mid-April
- Estimated end date: Early September
Project highlights:
- Trail surface repair: Sealing pavement cracks, repairing damaged sections of the trail surface and adjusting catch basin/manhole lids.
- Asphalt resurfacing: Application of a 1.5-inch asphalt overlay to provide a new, smooth trail surface.
- Safety improvements: Enhancement of trail user safety by replacing and refurbishing existing bollards and improving pavement markings.
- Kiosk renovations: Perform maintenance and reroofing of kiosk structures.
Estimated Project Timeframe:
Beginning in mid-April with anticipated completion in early September (Labor Day Weekend). Anticipated construction timeline is subject to change. Updates or delays will be reflected on this page.
Anticipated Trail Impacts:
Project Update: May 15, 2024
- Tree trimming and chipping is completed throughout the project area.
- Utility box and storm drain height adjustments are completed throughout the project area.
- Asphalt overlay has proceeded past the halfway point of the project area.
- Re-establishment of the shoulders of the trail commenced from State Line this week and continues along the project area.
- Safety painting, bollard refurbishment and kiosk work began this week.
Please note: All project areas remain closed.
Work on the trail shoulder is progressing this week.